December 20, 2021

Demo

January 1, 2022

Walls out and digging for sanitary sewer line for kitchenette sink

January 6, 2022

digging below ground to find sanitary sewer line

January 10, 2022

Locating sanitary line with help of camera

January 15, 2022

Studs up for new walls

January 18, 2022

Finally found the sanitary sewer line for kitchenette sink!

January 26, 2022

plumbing for kitchenette sink

February 5, 2022

floor filled with dirt and concrete; wood floor replaced and extended to hallway

February 19, 2022

extending cry room and bathroom wall to deck of roof for soundproofing; bathrooms painted

February 22, 2022

below ground plumbing for kitchenette approved 

March 3, 2022

above ground plumbing for kitchenette sink finished, inspected, and approved

March 5, 2022

more work on extending walls to roof for soundproofing

April 17, 2022

New drywall up

April 27, 2022

drywall work and new rooftop HVAC installed

April 30, 2022

Ceiling grid install

May 1, 2022

light grey speaker wall, other walls medium grey 

May 5, 2022

"contented" soft green cry room walls

May 9, 2022

new kitchenette floor and carpet tiles in cry room

May 12, 2022

dark gray accent kitchen, a/v booth, and entryway walls

 May 14, 2022

main room tv displays

May 16 & 23, 2022

A/V equipment setup; desk and countertop installed

May 18, 2022

refrigerator delivered

May 21, 2022

new floor in bathrooms, changing tables on wall, sink cabinet in kitchen

May 23, 2022

Kitchenette countertops and A/V booth countertop installed

May 24, 2022

Window removed, concrete cutout, emergency door installed

May 28-30, 2022

carpet installed, baseboards up, new blinds, ceiling tiles/panels complete, trash removed and space cleaned - ready for fire safety and occupancy/building final inspections! 

May 31, 2022

Waiting on final inspection

June 2, 2022

Cleanup on the eve of final inspection

June 3, 2022

We PASSED our final inspection and life safety!!!!

June 3, 2022

Final touches and clean up, getting ready to open on Sunday

June 4, 2022

Late night prepping for our first morning. Check out the cross shadow on the wall on the bottom picture!

June 5, 2022

Our first meeting!